We are involved in the implementation of major industrial projects.
Our company specialises in low- and high-voltage installations in all types of buildings. Our many years of experience and expertise enable us to guarantee you the highest quality of workmanship.
We have worked for clients in the following sectors:
The food industry
Construction: Liquid soup production hall
Client: Unilever Polska S.A.
Construction period: Q1 2006 – Q2 2006
Area: 7,500 m²
Scope of works (Construction of a liquid soup production hall):
GSZ low-voltage main switchboard, modernisation of the 15 kV MV switchboard, installation of acid-resistant steel cable tray routes for the food industry, cable distribution from the main MCC switchboard to the branch switchboard, including the installation of control systems
Scope of work (relating to ongoing cooperation with Unilever since 2003):
Ongoing modernisation of lighting, power and telecommunications systems in departmental halls, and modernisation of existing switchgear for production lines at the Poznań plant
Construction: Hochland cheese factory in Sovata, Romania
Client: HOCHLAND Romania SRL
Construction period: Q2 2006 – Q3 2006, Q4 2006
Scope of works (Q2 2006):
Installation of a 5-panel low-voltage switchboard, capacitor bank, and auxiliary power switchboard; connection of the low-voltage switchboard to the transformers via a 2500A busbar; laying of power cables to the evaporator; installation of lighting, power and socket systems, laying of cable routes, installation of equipotential bonding and lightning protection systems.
Scope of works (Q4 2006): installation of external lighting on the facades of production halls and technical buildings, installation of car park lighting, installation of the power supply system for the entrance gates to the car park and the plant site.
Project: Modernisation and extension of the LECH brewery in Poznań
Client: Kompania Piwowarska S.A. Lech Browary Wielkopolskie
Duration: Ongoing collaboration from 1998 to 1999
Area: 11,000 m²
Volume: 73,000 m³
Scope of work: high-voltage installations: installation works including pneumatics in the CKT filtration and fermentation departments, BBT yeast tank intermediate tanks, maturation, brewhouse, central CIP cleaning system, CO2 recovery and refrigeration plant, lighting, power, grounding and earthing systems.
Project: Wrigley chewing gum factory in Poznań
Client: Wrigley Poland Sp. z o.o.
Duration: ongoing collaboration between 1994 and 1995
Area: 9,000 m²
Volume: 50,000 m³
Scope of work: high-voltage installations: 2x1600 kVA transformer station, power supply and lighting for the installations, external lighting.
The chemical and pharmaceutical industries
Project: GlaxoSmithKline pharmaceutical plant in Poznań
Client: GlaxoSmithKline
Duration: Ongoing collaboration from 1998 to 2003
Area: 16,000 m²
Volume: 240,000 m³
Scope of work: high-voltage installations: electrical and process installations for the laboratory building and high-bay warehouse, and replacement of 15/0.4 kV transformers.
Construction: Superfos plastic packaging production plant in Lubień Kujawski
Client: “Superfos Włocławek” Sp. z o.o.
Main Contractor: Budimex Western
Branch Construction period: Q3 2005 – Q2 2006
Scope of works: Installation of the complete range of high- and low-voltage systems for the facility, including, amongst others: sub-distribution boards, interior hall lighting, power supply to process equipment, installation of plug sockets, power supply to main ventilation and air-conditioning switchboards, fire alarm systems, gas extinguishing systems in the server room, and site lighting.
Preparation of the complete detailed design and as-built drawings.
Supply of a prefabricated transformer station.
Project: Construction of a detergent tablet factory in Nowy Dwór Mazowiecki
Client: Reckitt Benckiser Poland S.A.
Construction period: Q1 2005 – Q2 2005
Area: 10,000 m²
Volume: 100,000 m³
Scope of works: transformer station, full-scope high-voltage electrical installations carried out in the production and storage hall of the Detergent Tablet Factory
Construction: Polpharma pharmaceutical plant in Starogard Gdański
Client: Polpharma S.A.
Completion date: Ongoing collaboration from 1999 to 2004
Area: 45,000 m² Volume: 274,000 m³
Scope of work: high-voltage installations in the Dry Formulation Plant, High-Bay Warehouse and Laboratory: power, lighting and power supply systems for production equipment in rooms with high hygiene requirements. A transformer station and power supply
systems for laboratory equipment were installed
The automotive industry
Construction: MERCEDES-BENZ engine production plant in Jawor – Hall H3
Client: MERCEDES-BENZ Manufacturing Poland Sp. z o.o.
Construction period: Q1 2018 – Q2 2020
Scope of work: installation of high-voltage electrical systems
Construction: UMICORE electric vehicle battery component factory in Radzikowice
Main Contractor: Siemens sp. z o.o.
Construction period: Q1 2020 – Q3 2020
Scope of work: installation of high-voltage electrical systems
Construction: Mahle piston and engine parts factory in Krotoszyn
Client: Mahle Polska Sp. z o.o.
Duration: Ongoing collaboration since 2003
Area: 70,000 m²
Volume: 700,000 m³
Scope of work: high- and low-voltage installations, including MV and LV lines, busbars, MV and LV switchgear, and foundry line installations. Replacement of a 16 MVA transformer with a 40 MVA transformer in the 110/15 kV substation, replacement of current transformers, and busbar installation on the circular enclosure frames in the 15 kV switchgear bays.
Construction: Volkswagen Crafter production plant in Września
Investor / Client: Volkswagen Poznań Sp. z o.o.
Project duration: Q1 2015 – Q4 2016
Scope of work: comprehensive installation of high-voltage electrical systems, design work, construction of the main substation (GPZ) including a 110kV cable line
Construction: MERCEDES BENZ battery production plant in Jawor
Main Contractor: TAKENAKA EUROPE GmbH Sp. z o.o.
Construction period: Q2 2019 – Q3 2020
Scope of work: execution of internal high-voltage electrical works, including workshop design
Construction: Construction of the Bridgestone Tyre Factory in Poznań and extension to include Halls 7 and 8
Client: Bridgestone Poland S.A.
Duration: Ongoing collaboration from 1998 to 2005
Area: 14,000 m²
Volume: 167,000 m³
Scope of work: high-voltage installations: MV and LV lines, internal and external lighting installations. An interesting feature is the lightning protection system mounted on 6-metre poles. In 2005, comprehensive electrical works were completed as part of the extension of production halls 7 and 8.
Construction: Gedia’s automotive parts manufacturing plant in Nowa Sól
Client: Gedia Nowa Sól
Duration: ongoing collaboration on a monthly contract basis since January 1998
Area: 26,300 m²
Volume: 315,000 m³
Scope of works: 20/04 kVA transformer station, MV and LV switchgear (ZMRs), cable lines and busbars, comprehensive installations: lightning protection, power, lighting in production halls, in the office building and high-bay warehouse, as well as low-voltage and anti-theft systems.
The electronics industry
Construction: FUNAI LCD TV assembly plant in Nowa Sól
Client: Funai Electric Polska
Contracting authority: Zueblin Polska
Construction period: Q1 2007 – Q2 2007
Area: 11,650 m²
Scope of works: 2 MV 20 kV feeder lines, 20/04 kV transformer station, 2x1250 kVA twin-transformer station, 2-section MV switchgear with automatic transfer switch, 2-section Rinn LV switchgear (6-pole), cable ladders and trays, internal power supply lines routed mainly in cable trays, meter panel, emergency and evacuation lighting, installations of plug sockets and socket outlets, computer socket installations
Installation of process and power equipment, including: power supply to the test area, power supply to ventilation and air-conditioning cabinets, power supply to the gas boiler room, power supply to the compressor room, power supply to the sewage pumping station, power supply to the fire pump station, power supply and internal installations in 2 reception areas, power supply and installation of battery-powered forklift charging points, installation of roof drain heating systems, equipotential bonding systems.
Installation of external lighting, including lighting for pavements and internal roads.
Telecommunications installations, including structured cabling, an access control system with time and attendance recording, a fire automation system, and a monitoring system.
Construction: LG Philips LCD factory in Kobierzyce
Client: LG – Philips LCD Poland Sp. z o.o. Consortium
Contracting authority: GS E&C Poland Sp. z o.o.
Construction period: Q2 2006 – Q2 2007
Area: 130,000 m² of built-up area, 63 ha of construction site
Scope of works: Installations in the main production building “Module Building” and in the other buildings: “Administration” (office block), “Utility” (technical block), “Boiler” (boiler house), Dining (Canteen), Security (Reception), 110kV Station (110kV substation).
Scope of high-voltage works: Laying MV power cables from the 110kV building to the other buildings, laying LV cables within the buildings, supply and installation of cable trays, supply and installation of fittings (switches and sockets), installation of luminaires (standard and emergency), installation of emergency lighting systems, installation of power and lighting distribution boards, connection of production lines, supply and installation of earthing and lightning protection systems.
Scope of low-voltage works: Supply and installation of public address and TV systems, supply and installation of telephone networks, supply and installation of fire alarm systems.
Outdoor (site) lighting installations and cable duct installations.
Construction: Kimball Electronics production plant in Sady near Poznań
Main contractor: Hochtief
Completion date: Q3 2008 – Q2 2009
Scope of work: installation of internal and external electrical and telecommunications systems, as well as the development of the electrical installation concept, construction and detailed design, and the provision of power to the building from the cable junction at the plot boundary, via the supply of a MV switchboard, transformers and a LV switchboard, supply and installation of building switchboards, cable routes, internal power supply lines, power and socket installations, lighting, earthing and lightning protection, as well as outdoor lighting installations, low-voltage installations: CCTV (closed-circuit television), Intrusion and Burglary Alarm System, and external telecommunications networks.
Other places of interest
Construction: LM Glasfiber propeller blade production plant in Goleniów
Client: LM Glasfiber
Completion date: Q3 2008 – Q1 2009
Area: 11,500 m²
As part of the works, our company carried out both high-voltage installations, including: the supply and installation of transformer station equipment (6-pole DRAWA MV switchgear and XEnergy LV main switchgear), the supply and installation of sub-switchgear;
as well as the construction of: MV and LV external networks; site lighting; internal power supply lines; earthing systems; plug sockets and power outlets; internal lighting systems;
as well as low-voltage installations, including:
structured cabling, telephone cabling; SAP fire alarm system, SSWiN/KD access control and intrusion detection system, gas detection.
Construction: Extension of the Sanitec Koło plant in Koło
Client: Sanitec Koło
Contracting authority: Budimex-Dromex S.A.
Construction period: Q3 2006 – Q2 2007
Area: 30,000 m²
Scope of works:
high-voltage installations, including: MV switchgear, 1000 and 630 kVA transformers, LV switchgear and building switchboards, cable tray and cable trunking systems, lighting installation, power and socket installation, earthing and lightning protection installation
Construction: Paroc production plant in Trzemeszno
Main Contractor: Broster Marek Brodecki & Mirosław Stec Sp. j. Construction Services Company
Project period: Q3 2019 – Q1 2020
Scope of work: Installation of high-voltage electrical systems and telecommunications cabling
Project: Philip Morris Cigarette Factory in Kraków
Client: Philip Morris
Construction period: 1999–2002
Production hall area: 3,500 m²
Production hall volume: 35,000 m³
Warehouse area: 3,500 m²
Warehouse volume: 22,700 m³
Scope of works: 0.4 kV low-voltage main switchboard, branch switchboards, UPS, internal power supply lines, power, lighting, earthing and equipotential bonding systems, emergency power supply, and low-voltage systems – fire protection and access control.